Foundation. Concrete forma nd rebar begin to appear - Click on a picture for a larger image

rebar is doweled into the existing foundation to connect it with the new footing
|
|

Rebar placed at the bottom of all of the underpinnings
|
|

The Sewer line has been moved and covered
|

This underpinning hole went under one side of the front door and back out the other side. Not exactly secure! |

In front of the living room the pads for the balcony supports, the hole for the greybeam and rebar for the pop-out window footing. |

The garage forms are coming along
|

Forms for the family room
|

Rebar for the office pop out window |
|

This hole under the entrance to the bathroom is about 5 feet deep.
|