Previous | September 27th, 2006 | Next

This seemed like a big day. Framing, Cleanup and MORE DEMO - Click on a picture for a larger image


The Cleanup crew came and removed the HUGE trash piles that were taking over the property

See, we have a driveway again

In the morning a huge load of Marvin Windows showed up.

Unloading Windows

By 9:00am the framers got all of the North side rafters in place

After more demo a new wall was suggested in the bathroom

Some of the top layer of plywood was placed on the 2nd floor


Zac and Jason Did some more major demo of ceilings.

The house now has no original ceiling except in a closet where the cedar lined walls still match a cedar ceiling.

Demo of the kitchen required some very careful cabinet protection and a lot of elbow grease.

After removing the maple crown molding the plaster was still very hard to remove from above the cabinets.

Kitchen Skylight!
 