Home | Daily Progress Photos | The Phases of Construction | The Timeline

Previous | November 13th, 2006 | Next

Framing, electrical, roof decking, plumbing- Click on a picture for a larger image


The Deck on the South side of the garage roof could be finished because it has no extended rafters. This will allow me to install my solar panel standoffs. There is still a ton of work to do to get the rafters finished on the rest of the house and our roofing, which was supposed to start today has been put way off.


More roof deck on the patio

Some sheathing

A stack of partially milled rafter tails

Roof rafters and standoffs over the master bedroom

Sheathing on the North Wall

Our Plumber, Elvis, came to install vent jacks through the roof

And our electrician, Serge, came to install the master panel and mast so that we can transfer the service line off the temporary pole and have it moved out of the way in time for roofing.
Previous | November 13th, 2006 | Next